In Ghaznavi v. Arby Constr., Inc., No. 14-24-00213-CV, 2025 Tex. App. LEXIS 839, the Court of Appeals of Texas (Court of Appeals) considered whether the trial court properly excluded the plaintiffs’, Kambiz Moavenzadeh Ghaznavi and Anahita Nokkonejad (collectively, the Ghaznavis), liability expert. The case arose from a fire at the Ghaznavis’ residence. The trial court held that because the Ghaznavis’ expert did not physically inspect certain fire damaged areas before they were repaired, the expert’s testimony was unreliable and thus inadmissible. The Court of Appeals reversed the lower court’s ruling, finding that the expert’s review of photographs of the repaired areas and his testimony explaining his opinions were sufficient to survive summary judgment.
In this case, the Ghaznavis’ hired the defendant, Arby Construction Inc. d/b/a National Residential Services (Arby Constr.), to install new tiling in a corridor inside their home. The corridor was adjacent to the garage. While Arby Constr. was performing the work, the Ghaznavis asked the defendant to fix an outlet inside the garage that was not working. Arby Constr. installed a new wire that connected the outlet to the garage door opener at the ceiling of the garage. Less than 2 months later, a fire occurred in the garage area. The fire marshal placed the origin of the fire in the ceiling of the corridor adjacent to the garage. The fire marshal’s report stated that “faulty wiring in the corridor behind the garage” caused the fire.
The Ghaznavis filed a lawsuit against Arby Constr. in November 2021 for damages related to the fire. In June 2022, over 17 months after the fire, the plaintiffs’ retained an electrical engineer to investigate the origin and cause of the fire. By this time, the corridor had been remediated, but the outlet in the garage was still in its immediate, post-loss condition. The engineer inspected the outlet and garage and reviewed the fire marshal’s photographs of the adjacent corridor. The engineer opined that the fire originated at the connection between an LED lamp and the outlet rewired by the defendant. The engineer further opined that the outlet became overstressed, generating heat over time until it caused the fire.
After the Ghaznavis’ expert engineer was deposed and produced a written report, Arby Constr. objected to the admissibility of the engineer’s opinion, arguing that it was unreliable because the engineer admitted he did not and could not inspect the location where the fire marshal determined the fire had originated. Arby Constr. also filed a motion for summary judgment on grounds that it did not perform any work in the area in which the fire marshal concluded the fire started. The trial court agreed that the engineer’s opinion was unreliable and granted the defendant’s motion for summary motion.
The Court of Appeals acknowledged that, regarding expert admissibility, it must consider not only whether the expert’s methods are grounded in science, but also whether the facts to which the expert applied his methods are reliable. If an expert’s opinion is based on certain assumptions about the facts, then the court must consider evidence showing that those assumptions were baseless. The court also recognized that the plaintiff bears the burden to account for plausible alternative causes. An expert’s failure to rule out other causes renders his opinions merely speculative.
The Court of Appeals found that while the plaintiffs’ expert did not inspect the corridor before it was repaired, his review the fire marshal’s photographs and his deposition testimony explaining why he disagreed with the fire marshal were sufficient to deem his testimony reliable and admissible. The plaintiffs’ expert testified that the fire damages in the area in the garage near the outlet were more severe than the damage in the corridor, indicating that the garage was the origin point. The engineer explained that the fire marshal’s photographs established that the fire patterns on the wood in the corridor ceiling showed that the fire was not burning as long in that area as the damage found in the garage and thus could not have started there. The Court of Appeals found that the engineer provided a sufficient basis for his conclusions and the process by which he adequately excluded the fire marshal’s original location of the fire. Thus, it reversed the lower court’s rulings.
The Ghaznavi case establishes that, in Texas, an expert may form opinions on the origin of a casualty without a physical inspection if the expert adequately relies on other evidence, such as photographs, to support the expert’s opinion and process. This case is helpful to subrogation professionals handling matters where the scene was modified prior to the completion of the origin and cause investigation. If the scene is properly documented and/or there is other data that an expert can rely on to support opinions regarding origin and cause, then it may be worth proceeding with recovery efforts.
Recent Posts
Categories
- Construction Defects
- Contracts
- Subrogation
- Products Liability
- Arbitration
- Indiana
- Economic Loss Rule
- CPSC Recalls
- Damages
- Statute of Limitations-Repose
- Illinois
- Negligence
- New York
- Limitation of Liability
- Colorado
- Virginia
- Massachusetts
- Experts - Reliability
- South Carolina
- New Jersey
- Certificate of Merit
- California
- Anti-Subrogation Rule
- Jurisdiction
- Landlord-Tenant
- Sutton Doctrine
- Maryland
- Waiver of Subrogation
- Uncategorized
- Pennsylvania
- Indemnification
- Causation
- Florida
- Condemnation
- CPSC Warning
- Minnesota
- Rhode Island
- Cargo - Transportation
- Malpractice
- Spoliation
- Tennessee
- Michigan
- Comparative-Contributory Negligence
- Contribution-Apportionment
- AIA Contracts
- Product Liability
- Assignment
- Missouri
- Parties
- Public Policy
- Civil Procedure
- Res Judicata
- Damages – Personal Property
- West Virginia
- Wyoming
- Oklahoma
- Builder's Risk
- Contractual Subrogation
- Equitable Subrogation
- Georgia
- Insurable Interest
- Mississippi
- Made Whole
- Delaware
- Settlement
- Subrogation – Equitable
- Construction
- Premises Liability
- Joint or Several Liability
- Montana
- Duty
- Privity
- New Mexico
- Right to Repair Act
- Landlord
- Tenant
- Building Code
- Arizona
- Evidence
- Experts – Daubert
- Litigation
- Texas
Tags
- Construction Defects
- Contracts
- Construction Contracts
- Subrogation
- Products Liability
- Indiana
- Arbitration
- Economic Loss Doctrine
- Illinois
- Mediation
- Damages
- Product Liability
- Statute of Limitations
- Negligence
- Statute of Repose
- Spoliation
- Cyber Subrogation
- Limitation of Liability
- New York
- Waiver of Subrogation
- Architects-Engineers
- Landlord-Tenant
- Statute of Limitations – Discovery Rule
- CPSC Recalls; Products Liability
- Massachusetts
- Circumstantial Evidence
- Experts – Daubert
- New Jersey
- Colorado
- Oklahoma
- Certificate of Merit
- Incorporation by Reference
- Virginia
- Indemnification
- Maryland
- Economic Loss Rule
- Amazon-eBay
- Contracts - Enforcement
- Malfunction Theory
- Pennsylvania
- Georgia
- Louisiana
- California
- Civil Procedure
- Jurisdiction
- Jurisdiction - Personal
- Gist of the Action
- Sutton Doctrine
- Florida
- Public Policy
- Causation
- Arizona
- Anti-Subrogation Rule
- Condemnation
- Inverse Condemnation
- Tennessee
- West Virginia
- Negligent Undertaking
- Statute of Limitations - Contractual
- Minnesota
- Statute of Limitations - Accrual
- Delaware
- Experts – Qualifications
- Improvement
- Negligence – Duty
- Connecticut
- Apportionment
- Privity
- Design Defect
- Rhode Island
- Statute of Limitations - Tolling
- Expert Qualifications
- Malpractice
- Amazon
- Evidence - Hearsay
- Made Whole
- Loss of Use
- Vehicles
- Settlement
- workers' compensation subrogation
- Warranty - Implied
- Michigan
- Comparative Fault
- Water Damage
- Condominiums
- Contracts - Formation
- Non-Party at Fault
- Malfunction Theory; Design Defect
- Independent Duty
- Ohio
- Wisconsin
- Unconscionable
- Missouri
- Parties
- Failure to Warn
- Manufacturing Defect
- Pleading
- Removal
- Entire Controversy Doctrine
- Motion to Intervene
- Res Judicata
- Subrogation; High-Net-Worth; Damages; Art; Cargo-Transportation; Anti-Subrogation Rule
- Products Liability – Risk-Utility
- Lithium-ion battery
- Internet Sales
- Anti-Subrogation Rule; Wyoming; Landlord-Tenant; Sutton Doctrine
- Sanctions
- Spoliation – Fire Scene
- Builder’s Risk
- Contractual Subrogation
- Equitable Subrogation
- Exculpatory Clause
- Gross Negligence
- Insurable Interest
- Mississippi
- Daubert
- Standing
- Third Party
- Accepted Work
- Montana
- Independent Contractor
- Res Ipsa
- New Mexico
- Right to Repair Act
- AIA Contract
- Betterment
- Damages-Code Upgrades
- Statute of Limitations - Repose
- Washington
- Implied Warranty of Habitability
- Warranty - Construction
- Idaho
- Joint-Tortfeasors
- Forum-Venue
- Warranty – Express
- AIA Contracts
- Anti-Indemnity Statutes
- Products Liability - Foreseeability
- Cargo-Transportation
- Contribution
- MCS-90
- Substantial Completion
- Evidence
- Experts
- Experts - Reliability
- Litigation
- Texas
Authors
Archives
- December 2025
- November 2025
- September 2025
- August 2025
- July 2025
- May 2025
- April 2025
- March 2025
- February 2025
- January 2025
- December 2024
- November 2024
- October 2024
- September 2024
- August 2024
- July 2024
- June 2024
- May 2024
- April 2024
- March 2024
- February 2024
- January 2024
- December 2023
- November 2023
- October 2023
- September 2023
- August 2023
- July 2023
- June 2023
- May 2023
- April 2023
- March 2023
- February 2023
- January 2023
- December 2022
- November 2022
- October 2022
- September 2022
- August 2022
- July 2022
- June 2022
- May 2022
- April 2022
- March 2022
- February 2022
- January 2022
